Overview

In 2018, Napier-Reid provided a water treatment system to the Eel Ground First Nation Water Treatment Plant in Big Hole Tract, New Brunswick.

The system is designed to handle a production flow of 48 m³/day of well water for treatment into water meeting or exceeding Canadian Drinking Water Quality Guidelines.

The scope of supply outlined by Napier-Reid includes: two free standing filters, two Grundfos well pumps, a carbon steel skid, two lots of inlet piping, two inline static mixers, two chemical injection systems, a 100 L chemical day tank, a pressure tank, a UV system, one lot of monitoring and control instruments, a NEMA4 control panel, a PLC control panel, and copies of shop drawings and manuals.